COMP 465W: Software Engineering
Fall 2015
Detailed Project Schedule
Introductory write-up (not graded) of approved project: 9/11/2015
Draft of the Requirement Specification (SRS)
document: 10/2/2015
SRS document: 10/14/2015
Draft of the Design Document: 10/26/2015
The first rewrite of the SRS document: 11/2/2015
Design Document: 11/9/2015
The first rewrite of the Design Document: 11/16/2015
Draft of the Test Plan Document: 11/23/2015
Test Plan Document: 12/2/2015
The second rewrite of the SRS document: 12/7/2015
The second rewrite of the Design Document: 12/11/2015
User Manual: 12/18/2015
Test Report: 12/18/2015
Project Presentation in class: 12/11/2015 or 12/14/2015
Complete project, including the rewrites of the test
report and the user
manual is due Friday, 12/18/15, midnight.